425 Oxford Street

Installation of external glazing, doors, cladding and canopy

Project Story

We were contracted by Sir Robert McAlpine Ltd to carry out the installation of external glazing, doors, cladding and canopy as part of the refurbishment of 425 Oxford Street London. The lower levels of the building were to be retail space and the new flagship store for Adidas.

The works comprised of design, manufacture and installation of double storey height, 6-metre-high  facade external glazing to the retail space, supported on a bespoke laser cut steel box section framing system designed and engineered by us specifically for the project.

We also installed bespoke powered automatic frameless glass double doors to the main entrance office space with powered bifold security gates for night-time/out of hours security, along with a bespoke entrance canopy with bronze anodised aluminium soffit, flank and fascia panels.

We were also responsible for the design and installation of both fire-rated and non-fire rated PPC finished steel window systems to the upper levels and external security doors to various locations around the building

Project Summary

425 Oxford Street OAG Architectural Glass Facades 02
425 Oxford Street OAG Architectural Metal Cladding 03
425 Oxford Street OAG Architectural Metal Cladding 04
425 Oxford Street OAG 05
425 Oxford Street OAG 06
425 Oxford Street OAG 07
Oxford Street 425 OAG Architectural Glass Canopies
425 Oxford Street OAG 09
425 Oxford Street OAG 08
6m High

external glazing façade

Bronze

anodised aluminium

Project Story Continued

There were a couple of restrictions that we needed to accommodate to complete this project. One being noise restriction (the upper levels of the building remained fully occupied throughout the refurbishment) and the other being the fact that Oxford Street is a busy thoroughfare. The retail glazing installation to three elevations of the building was carried out over a continuous series of night working, commencing at 10pm each evening. The huge high-performance double-glazed units measuring up to 6 metres x 2.6 metres and each weighing 1000kg, were delivered to site at the start of each night-time shift, manoeuvred into place and installed using a mini crane. Following completion of each glazing shift, all plant materials were removed prior to 6am each morning.

Following the design phase, we commenced work on site during early August 2018 and the works were completed April 2019 with final client handover in June 2019.

Thanks for sharing!

425 Oxford Street OAG Architectural Glass Shop Fronts 01

425 Oxford Street

Have a project for us?
Let's discuss it!

425 Oxford Street

425 Oxford Street, London, UK

Installation of external glazing, doors, cladding and canopy